Guide to Daily Inspections of Magnetizing Equipment: How to Create a Standard Inspection Checklist?
End-to-End Solution for Magnetization Automation
Automated Magnetic Charging Integrated Solution
After continuous operation of the magnetizing equipment, the parameters of the capacitors, coils, and power supply will gradually drift. If inspections are not performed promptly, the magnetizing results may gradually deteriorate without notice. Creating a simple, actionable inspection checklist is more convenient than waiting for problems to arise before making repairs.

Before turning on the equipment each day, check three things first. First, grounding and emergency stop: Ensure the grounding terminals are secure and that the emergency stop button can properly interrupt the charging process. Second, cooling: For water-cooled systems, check the flow rate and liquid level; for air-cooled systems, check the airflow. Insufficient cooling will directly reduce magnetization saturation. Third, capacitor voltage: Charge under no-load conditions until the set value is reached, and observe whether the voltage meets the standard and if there are any abnormal drops.

Add three tasks each week. First, magnetize the equipment once using a standard sample, measure the average magnetic flux, compare it to the reference value, and calibrate the equipment if there is a significant deviation. Second, inspect the exterior of the magnetizing coils for signs of overheating, discoloration, or damaged insulation. Third, clean dust and metal shavings from the interior of the equipment to prevent electrical discharges and sparks. Conduct a more comprehensive inspection once a month. Measure the grounding resistance to ensure it is within the required range; use a bridge to measure the coil’s inductance and resistance, and replace the coil promptly if there are significant deviations; review the equipment parameter records to analyze long-term trends.

Printing these items on an inspection checklist and having them signed off on by each shift is more reliable than relying on operators’ memories. When Jiuju Automation delivers its magnetizing equipment, it provides inspection checklist templates and parameter recording formats that cover daily, weekly, and monthly inspection items and standard values. For on-site management, Jiuju Automation recommends archiving inspection data on a monthly basis and using trends to assess component aging, thereby scheduling maintenance before failures occur and reducing unplanned downtime.
Magnetization of Magnetic Materials
3C Electronic Magnetization
Motor Rotor Magnetization
Car Speaker Magnetization
New Energy Vehicle Industry
Medical Equipment Industry
Other Industries
Jiu Ju Magnetizer